11,76 % Production of heat via boilers Fig. 8: Simulation of the system’s functioning on a typical summer’s day
71,45 % Production of heat via a CHP system (production of heat and power evaluated by the Cogencalc© software
16,79 % Production of heat via solar panels package). The heat requirements of the absorption chiller account for
-61,83 % Heat needed for the absorption machine 38% of total hot water requirements. The remainder is used for the
-38,17 % Heat needed for producing hot water building’s sanitary facilities. Total hot water demand is thus covered by
means of solar thermal panels (+/- 17 %), the CHP system (+/- 72 %) and
supplementary boilers (+/- 11 %).
Fig. 9: Building energy performance unit (BEPU) of the Charleroi fire station.
(Orange: BEPU 13 of the “miscellaneous” zone – Blue: BEPU of the “office” zone – Green: BEPU of the “production” zone).