The stability of the construction in the first phase was further ensured by adding
temporary cables. Upon completion of the second phase of the structure, these
pulling cables will be moved one by one.
The placing of roof sheeting and glass elements in skylights and ventilation
shafts is done during the day. These works are executed directly following the
installation of the roof structure. Safety nets prevent objects from falling on the
areas underneath. Additional safety zones on the platforms are closed off.
For the mounting of the glass parts of the elevator shafts, only a separate area on
the platform had to be closed off.
The mounting of glass parts in the small canopies under the cover and in the vertical
fronts is done after the roof structure is erected. Small scaffoldings and elevated
work platforms are used. A small zone on the platform had to be closed off.