112 December 2012
the sag of the concrete slab above the car park ( nal situation, taking account of creep) 2012
2013 2014
2012-12
Site preparation and groundwork
Foundation posts and foundation basement
Massive concrete slabs and columns on ground level; shell work basement First- oor slab
Concrete core activation in oor slabs Second- oor slab
Roof slab
Assembly main staircase
Steel structure gallery
Roof covering
exterior woodwork and bamboo facade covering
Wooden terraces and interior gardens Second facade in glass panels
Technical installations in shafts or under the raised oor Installation of raised oors
Drywall partitions and spray-plaster ceilings
Lifts
Interior woodwork
Wood ooring and carpet
Kitchen and restaurant
Technical installations in basement; BTES eld; PV panels
Surround works Delivery